Case study · MarLuc synopsis
Network Rail machine learning project forecasting
DImplemented 2020 onwards · Transport and logistics · UK · 3 min read · Version 1.0
Network Rail tested nPlan's machine learning forecasting on two large projects and in 2020 said it would roll it out to 40 projects, then all projects. Its reported result is a retrospective estimate of savings; results from the rollout are not reported.
At a glance
- AI used
- Machine learning (deep learning) forecasting of project schedules and risk, from nPlan
- Implemented
- 2020 onwards
- Grade
- Band D · Task support · Claimed only
- Headline result, as reported
- Trial on two projects worth over £3bn found up to £30m of savings could have been made on one of them, by Network Rail's account (2020)
1The case
The facts, as reported by the sources below. Where a source is silent, the field says “Not reported”.
Organisation
Network Rail. Owner and operator of Britain's railway infrastructure, including 20,000 miles of track and 30,000 bridges, tunnels and viaducts. It manages and delivers thousands of projects a year in its Railway Upgrade Plan.
Canvas block: 4. Operations and process. Also 6. Data and technology
Business challenge
The challengeNetwork Rail wanted accurate cost and time forecasts to reduce the risk of project overruns and improve reliability for passengers. The supplier argues that the established method, quantitative schedule risk analysis, gives generally inadequate results and takes ten times longer; a project management consultant told ENR a major analysis can take two to three months.
How it was addressedNetwork Rail worked with London start-up nPlan, whose software learns from past projects by comparing what was planned against what actually happened at individual activity level. It tested the tool on the Great Western Main Line and the Salisbury to Exeter signalling project. In October 2020 it announced a rollout to 40 projects, then all Network Rail projects by mid-2021. In 2022 the Transpennine Route Upgrade, a multi-billion-pound programme between York, Leeds, Huddersfield and Manchester, agreed a deal with nPlan; its head of strategic programme controls said the tool allowed more frequent analysis of more schedules, and nPlan said the programme intended to use it in place of quantitative schedule risk analysis. [1][2][3][4]
Who implemented it
- nPlanSoftware vendorSupplied the machine learning forecasting and risk analysis software
Technology (SEAM pillar E)
- T1
- T2
- T3
- T4
- T5
- T6
- T7
- T8
- T9
- Deployment
- Not reported
- Vendors and products
- nPlan, nPlan risk analysis and assurance
- Where it was built in
- Applied to project schedules: the model learns from past projects by comparing planned and actual performance at activity level, then forecasts outcomes and flags risks to project teams. [1][3]
Technology types follow the SEAM taxonomy, the same list the SEAM Check uses.
What changed
Before: schedule risk assessed through quantitative schedule risk analysis, which relies on workshops and takes months, per ENR. After: machine learning forecasts from historical project data flag risks to project teams, by Network Rail's account. Whether the rollout reached all projects: Not reported. [1][2][3][4]
What it cost
Not reported
What it saved
Governance and control
Forecasts flag risks to project teams, who mitigate them. Network Rail's programme director (affordability) spoke for the partnership. Accountable owner, validation of forecast accuracy and review: Not reported.
- Accountable owner: Not reported
- Safe use: Not reported
- Human in the loop: Claimed
- Monitoring and assurance: Not reported
- Vendor AI: Not reported
- Agent controls: Not reported
- Standards and regulation: Not reported
Controls on each card:EvidencedOutside scrutinyClaimedMissingNot reported
| SEAM point | Evidence | What was done and how it was applied |
|---|---|---|
| S2 · Accountable owner | ○ Not reported | Not reported. |
| A1 · Safe use | ○ Not reported | Not reported. |
| A2 · Human in the loop | ◐ Claimed | Flagged risks go to project teams, who mitigate them before they occur, by Network Rail's account. [1] |
| A3 · Monitoring and assurance | ○ Not reported | Not reported. |
| A4 · Vendor AI | ○ Not reported | Not reported. |
| A5 · Agent controls | ○ Not reported | No agents described. |
| A6 · Standards and regulation | ○ Not reported | Not reported. |
● Evidenced: shown by an independent source. ◐ Claimed: the organisation's own account. ✕ Missing: an independent source shows the control was absent. ○ Not reported: the sources are silent.
What worked, what did not, what is unproven
Worked
- The trial flagged risks that project teams had not seen, by Network Rail's account.
- The Transpennine Route Upgrade said the tool let it analyse more schedules more often, which it said it lacked the resources to do with the established method.
Did not
- Not reported
Unproven
- Whether the rollout reached all Network Rail projects by mid-2021.
- Realised savings or fewer overruns on live projects.
- Forecast accuracy, which no source opened reports independently.
2Grade and SEAM assessment
MarLuc's opinion, made on the evidence above. How we grade cases
Level of change and impact
- ATransformational
- BOperating model redesign
- CProcess changeClaimed
- DTask supportGraded · Claimed only
- ENo measurable effect
- FFailure
- Claimed
- C
- Grade
- D · Task support
- Proof
- Claimed only
- Level of change
- Task support
Task support (Level 1, band D), claimed as process change (band C). Forecasts inform project teams; no change in project outcomes is published.
Graded D, claimed C. The forecasts support project teams, who decide what to do about flagged risks. The trial result is a retrospective estimate, and no results from the wider rollout are published. A rail upgrade programme said it intended to replace its established risk method with the tool, which would be a process change if shown.
Controls against the SEAM minimum
Controls not reported, so this cannot be checked. For T8 Predictive / ML models, the SEAM minimum is monitoring; the sources do not report any controls.
Project teams receive flagged risks and decide on mitigation; validation of forecasts not reported.
The SEAM view and lessons learnt
The design keeps people at the decision point: the model flags risks and project teams act on them. The gap is evidence. The headline saving is a retrospective estimate, and no later results are published. A larger organisation adopting predictive project tools should track forecasts against outturn on live projects before relying on them.
- Track forecasts against actual outcomes on live projects.
- Report realised savings separately from retrospective estimates.
- Keep project teams accountable for acting on flagged risks.
Evidence
Score 1 of 4. Self-reported: Network Rail's announcement, and statements by the supplier and a programme client in trade press; no independent evaluation.
Evaluation method. Self-reported company figures: a retrospective trial on two projects, announced by Network Rail in October 2020.
Sources disagree. Network Rail says up to £30m of savings could have been achieved; Construction Management described it as a theoretical saving. Bent Flyvbjerg of Oxford's Saïd Business School told ENR that high-quality data helps de-bias projects, but that leaders also need ambition to beat the historical track record.
Status. Unclear: rollout to all projects was planned for mid-2021; no later Network Rail results found in sources opened. The Transpennine Route Upgrade agreed a deal with nPlan in 2022.
3Original sources
This synopsis draws on 4 sources, summarised by MarLuc. Read them in full before relying on any figure. If you think we have a fact or a grade wrong, challenge it and we will check and reply.
- [1]Network Rail: Network Rail using innovative technology to transform project planning and delivery (October 2020) (opens in a new tab)networkrailmediacentre.co.uk
- [2]Construction Management: Machine learning identifies £30m saving for Network Rail (October 2020) (opens in a new tab)constructionmanagement.co.uk
- [3]ENR: nPlan promises better risk management through AI for $11B UK rail project (November 2022) (opens in a new tab)enr.com
- [4]KHL Construction Europe: UK rail turns to artificial intelligence (November 2022) (opens in a new tab)khl.com
Version 1.0 · Published 16 Nov 2026 · Updated 16 Nov 2026 · Facts checked against sources 16 Nov 2026
Version history
- v1.016 Nov 2026First published
Related case studies
Found this useful? Share it with your network.