Case study · MarLuc synopsis

Network Rail machine learning project forecasting

D

Implemented 2020 onwards · Transport and logistics · UK · 3 min read · Version 1.0

Network Rail tested nPlan's machine learning forecasting on two large projects and in 2020 said it would roll it out to 40 projects, then all projects. Its reported result is a retrospective estimate of savings; results from the rollout are not reported.

At a glance

AI used
Machine learning (deep learning) forecasting of project schedules and risk, from nPlan
Implemented
2020 onwards
Grade
Band D · Task support · Claimed only
Headline result, as reported
Trial on two projects worth over £3bn found up to £30m of savings could have been made on one of them, by Network Rail's account (2020)

1The case

The facts, as reported by the sources below. Where a source is silent, the field says “Not reported”.

Organisation

Network Rail. Owner and operator of Britain's railway infrastructure, including 20,000 miles of track and 30,000 bridges, tunnels and viaducts. It manages and delivers thousands of projects a year in its Railway Upgrade Plan.

Canvas block: 4. Operations and process. Also 6. Data and technology

Business challenge

The challengeNetwork Rail wanted accurate cost and time forecasts to reduce the risk of project overruns and improve reliability for passengers. The supplier argues that the established method, quantitative schedule risk analysis, gives generally inadequate results and takes ten times longer; a project management consultant told ENR a major analysis can take two to three months.

How it was addressedNetwork Rail worked with London start-up nPlan, whose software learns from past projects by comparing what was planned against what actually happened at individual activity level. It tested the tool on the Great Western Main Line and the Salisbury to Exeter signalling project. In October 2020 it announced a rollout to 40 projects, then all Network Rail projects by mid-2021. In 2022 the Transpennine Route Upgrade, a multi-billion-pound programme between York, Leeds, Huddersfield and Manchester, agreed a deal with nPlan; its head of strategic programme controls said the tool allowed more frequent analysis of more schedules, and nPlan said the programme intended to use it in place of quantitative schedule risk analysis. [1][2][3][4]

Who implemented it

  • nPlanSoftware vendorSupplied the machine learning forecasting and risk analysis software

Technology (SEAM pillar E)

T8 Predictive / ML models
  1. T1
  2. T2
  3. T3
  4. T4
  5. T5
  6. T6
  7. T7
  8. T8
  9. T9
Deployment
Not reported
Vendors and products
nPlan, nPlan risk analysis and assurance
Where it was built in
Applied to project schedules: the model learns from past projects by comparing planned and actual performance at activity level, then forecasts outcomes and flags risks to project teams. [1][3]

Technology types follow the SEAM taxonomy, the same list the SEAM Check uses.

What changed

Before: schedule risk assessed through quantitative schedule risk analysis, which relies on workshops and takes months, per ENR. After: machine learning forecasts from historical project data flag risks to project teams, by Network Rail's account. Whether the rollout reached all projects: Not reported. [1][2][3][4]

What it cost

Not reported

What it saved

Retrospective trial estimate: savings of up to £30m could have been achieved on the Great Western Main Line, mainly by flagging unknown risks, by Network Rail's account. Construction Management called it a theoretical saving. Realised savings: Not reported. [1][2][3][4]

Governance and control

Forecasts flag risks to project teams, who mitigate them. Network Rail's programme director (affordability) spoke for the partnership. Accountable owner, validation of forecast accuracy and review: Not reported.

  • Accountable owner: Not reported
  • Safe use: Not reported
  • Human in the loop: Claimed
  • Monitoring and assurance: Not reported
  • Vendor AI: Not reported
  • Agent controls: Not reported
  • Standards and regulation: Not reported

Controls on each card:EvidencedOutside scrutinyClaimedMissingNot reported

Governance evidence by SEAM point
SEAM pointEvidenceWhat was done and how it was applied
S2 · Accountable owner○ Not reportedNot reported.
A1 · Safe use○ Not reportedNot reported.
A2 · Human in the loop◐ ClaimedFlagged risks go to project teams, who mitigate them before they occur, by Network Rail's account. [1]
A3 · Monitoring and assurance○ Not reportedNot reported.
A4 · Vendor AI○ Not reportedNot reported.
A5 · Agent controls○ Not reportedNo agents described.
A6 · Standards and regulation○ Not reportedNot reported.

● Evidenced: shown by an independent source. ◐ Claimed: the organisation's own account. ✕ Missing: an independent source shows the control was absent. ○ Not reported: the sources are silent.

What worked, what did not, what is unproven

Worked

  • The trial flagged risks that project teams had not seen, by Network Rail's account.
  • The Transpennine Route Upgrade said the tool let it analyse more schedules more often, which it said it lacked the resources to do with the established method.

Did not

  • Not reported

Unproven

  • Whether the rollout reached all Network Rail projects by mid-2021.
  • Realised savings or fewer overruns on live projects.
  • Forecast accuracy, which no source opened reports independently.

Timeline

  1. Oct 2020Network Rail reports trial results and plans rollout to 40 projects, then all projects by mid-2021[1]
  2. Nov 2022Transpennine Route Upgrade agrees a deal with nPlan for AI forecasting and risk management[4]

2Grade and SEAM assessment

MarLuc's opinion, made on the evidence above. How we grade cases

Level of change and impact

  1. ATransformational
  2. BOperating model redesign
  3. CProcess changeClaimed
  4. DTask supportGraded · Claimed only
  5. ENo measurable effect
  6. FFailure
Claimed
C
Grade
D · Task support
Proof
Claimed only
Level of change
Task support

Task support (Level 1, band D), claimed as process change (band C). Forecasts inform project teams; no change in project outcomes is published.

Graded D, claimed C. The forecasts support project teams, who decide what to do about flagged risks. The trial result is a retrospective estimate, and no results from the wider rollout are published. A rail upgrade programme said it intended to replace its established risk method with the tool, which would be a process change if shown.

Controls against the SEAM minimum

Controls not reported, so this cannot be checked. For T8 Predictive / ML models, the SEAM minimum is monitoring; the sources do not report any controls.

Project teams receive flagged risks and decide on mitigation; validation of forecasts not reported.

The SEAM view and lessons learnt

The design keeps people at the decision point: the model flags risks and project teams act on them. The gap is evidence. The headline saving is a retrospective estimate, and no later results are published. A larger organisation adopting predictive project tools should track forecasts against outturn on live projects before relying on them.

  1. Track forecasts against actual outcomes on live projects.
  2. Report realised savings separately from retrospective estimates.
  3. Keep project teams accountable for acting on flagged risks.

Evidence

Score 1 of 4. Self-reported: Network Rail's announcement, and statements by the supplier and a programme client in trade press; no independent evaluation.

Evaluation method. Self-reported company figures: a retrospective trial on two projects, announced by Network Rail in October 2020.

Sources disagree. Network Rail says up to £30m of savings could have been achieved; Construction Management described it as a theoretical saving. Bent Flyvbjerg of Oxford's Saïd Business School told ENR that high-quality data helps de-bias projects, but that leaders also need ambition to beat the historical track record.

Status. Unclear: rollout to all projects was planned for mid-2021; no later Network Rail results found in sources opened. The Transpennine Route Upgrade agreed a deal with nPlan in 2022.

3Original sources

This synopsis draws on 4 sources, summarised by MarLuc. Read them in full before relying on any figure. If you think we have a fact or a grade wrong, challenge it and we will check and reply.

Version 1.0 · Published 16 Nov 2026 · Updated 16 Nov 2026 · Facts checked against sources 16 Nov 2026

Version history
  1. v1.016 Nov 2026First published

Found this useful? Share it with your network.

Know an AI deployment we should grade? Submit a case study

Where does your organisation sit?

The free SEAM Check takes ten minutes and shows where AI value is leaking. The free SEAM Report then gives your leadership team the full picture.